METHODOLOGY
The scope of work required a combination of process synthesis and RAM engineering to analyze and quantify the performance of the existing plants compared to the new conceptual design.
Analyzing and quantifying numerous design options, optimizing equipment redundancy and using the historical maintenance records from other plants to simulate reliability and optimize the full lifecycle costs elements, CAPEX, OPEX and REVEX (Production availability) for the new design.
ProAIM’s consultants worked with the customer throughout the 7 steps of the project, screening data, analysis, simulation, FMECA, RCM review and joint workshops to ensure that the final recommendations were fully assessed and agreed upon in terms of risks.